“DO” • Grout shear
keys before floor is loaded and before joints fill with debris.
• Ensure grout has reached required strength before loading
of floor. • Use C35/10 concrete when grouting. •
Sufficiently wet shear keys before placing grout. • Prop
spans exceeding 3.0m at mid span before grouting. • Prop
all floors loaded with blocks. • Prop all cantilevered
slabs at extreme free edge. • Allow one cubic metre of
grout for every 75 sq. metres of flooring. • Cork and
scrim joints to reduce risk of cracking. • Read attached
information regarding your particular job. |

Slabs
must be grouted before work proceeds. |
“DO NOT” • Do not exceed loadings as indicated
on your customer drawings • Do not leave floor ungrouted.
• Do not grout with anything other than specified mix.
• Do not leave out any specified steel. • Do not
load floor before grout has cured. • Do not load unpropped
floors when span exceeds 3.0 metres. • Do not remove props
before loading removed. • Do not use impact tools when
fixing to or creating openings in slabs. • Do not plaster
direct until floor above has been completed.
|

Slabs
must remain propped until grout has cured and all construction
loads have been removed. |
WRITTEN APPROVAL MUST BE OBTAINED FROM OUR TECHNICAL DEPARTMENT
IN THE CASE OF ANY DEVIATION FROM THE ABOVE.